1 |
Draw general layout of modern thermal power plant with usual
notation. |
2 |
Explain
any six factors considered in selecting a site for big thermal power plant. |
3 |
Explain
the construction and working of Electrostatic Precipitator with neat sketch. |
4 |
Differentiate
between Superheater, Reheater and air Preheater. |
5 |
Compare
(i) Jet condenser with Surface condenser (ii) Natural draught cooling tower
and Mechanical draught cooling tower. |
6 |
Explain
necessity of feed water treatment. What are the major impurities present in
feed water? Explain in brief. |
7 |
Explain
with neat sketch construction of CANDU type reactor along with its merit and
demerits. |
8 |
Define
following terms: Connected load, Average demand, Maximum Demand, Diversity
factor, Utilization factor, Load factor, Plant capacity factor. |
9 |
Describe
a neat line diagram of in-plant coal handling system and explain the
equipment used at different stage. |
10 |
Classify
pulverized mill used in modern power plant. Explain any one with neat sketch. |
11 |
Classify
the condensers. Explain any one surface type condensers with neat sketch. |
12 |
Describe
Nuclear fuel briefly. Explain nuclear waste and its disposal methods. |
13 |
Explain
working principal of fluidized bed boiler with necessary diagram. |
14 |
Explain
nuclear fusion and fission process. Make a list of nuclear power plants of
India. |
15 |
Explain
with neat sketch construction and working of Lamont Boiler. Draw line diagram
of benson boiler. |
16 |
Explain
with neat sketch Boiling Water Reactor. What are the reasons of corrosion in
a boiler and how it is control? |
17 |
Compare
between Nuclear power plant and thermal power plant. |
18 |
With
neat sketch explain Pneumatic ash handling system. List its advantages and
disadvantages. |
19 |
The
peak load on a 50 MW power station is 39 MW. It supplies power through 07 2
four transformers whose connected loads are 17, 12, 9 and 10 MW. The maximum
demands on these transformers are 15, 10, 8, and 9 MW respectively. if the
annual load factor is 50% and plant is operating for 65% of the period in a
year, find out the following: (i) Average load on the station (ii) Energy
supplied per year (iii) Demand factor (iv) Diversity factor (v) Power Station
use load.-WINTER 2015. |
20 |
Calculate
the cost of generation per kWhr for a power station having following data:
Installed capacity of plant =200MW; Capital cost=Rs400; crores Rate of
interest and depreciation =12% Annual cost of fuel , salaries and taxation=Rs
5 crores; Load factor=50%. Also estimate the saving in cost per KWhr if
annual factor is raised to 60%.- SUMMER 2014 |
21 |
Derive
an expression for chimney height in order to obtain a draught of ‘h’ mm of
water column if the boiler used ‘m’ kg of air/kg of fuel. Assume, surrounding
air temperature as ‘Ta’ and flue gas temperature as ‘Tg’ in degree absolute.
Also derive an expression for the condition of maximum discharge of flue
gases through a chimney.- WINTER 2016 |
No comments:
Post a Comment