1.       Write short note on acceptance of tender.

2.        What is tender? Explain in brief classification of tender.

3.       Explain in detail various factors affecting the rate analysis.

4.       Explain in brief various data required for preparing a detailed estimate.

5.       Write short notes on following. (1) Contingencies (2) Work charged establishment charges.

6.       Work out rate analysis for 1st class brick Masonry work in cm (1:6) for super structure.

7.       Write short note on scrutiny of tender.

8.       Draft a typical tender notice for construction of Higher Secondary School building.

9.       Write detailed specifications for the following. 1. First class brick work in cm (1:6) 2. Reinforced Cement Concrete (1:2:4).

10.   What is specification? What are the objectives of writing specifications?

11.   Discuss in brief essential principles of writing good specifications.

12.   A trapezoidal sloped square footing has top dimension 0.6 m X 0.6 m and the base dimensions 1.2 m X 1.2 m with height of 0.8 m. Determine volume of concrete required for footing. Also find out surface area of sides.

13.   Explain in brief earnest money deposit and Security deposit.

14.   Explain in detail termination of contract.

15.    How the rent of the building is fixed? Explain in brief factors affecting the rent of a building.

16.   Explain in detail item rate contract.

17.   Explain in detail essential requirements of a valid contract.

18.   Explain in brief rental method of valuation.

19.   Explain the factors affecting the value of property.

20.   A scooter was purchased in Rs.60, 000. Assuming its salvage value at the end of 6 years to be Rs.15, 000. Determine the amount of depreciation for each year by (1) Straight line method (2) Constant Percentage method.

21.   Explain the following types of engineering contracts –( 1) Item Rate Contract (2) BOT percentage rate of contract ( 3) Lump Sum Contract.

22.   Write detail specifications for Earthwork in excavation in foundation.

23.   Define tender and draft a typical tender notice for civil engineering works.

24.   A machine is purchased for Rs-1,00,000. Assuming its life 12 years its 10%salvage value. Calculate the amount of depreciation at the end of third year in a tabular form by using following methods –( 1) Straight Line Method (2) Constant Percentage Method.

25.   How would you determine value of the property using rental method of valuation? Enumerate its advantages and limitations.

Discuss mode of payment to the contractor. How the first and final bill, running or interim bills are paid to contractor?